2012 Second Line Widening Phase 1

In June 2012, Avery Construction was awarded the contract for the Re-grading and Re-construction of Second Line East from Old Garden River Road heading east roughly 760M. The job consisted of installing both Sanitary and Storm pipe and structures as well as a new PVC water main. The job also required us to move roughly 30,000m3 of material to achieve the required grade.